Updated Phasing Plans June 2025

With work well under way to deliver the Ashbourne Reborn programme, updated phasing plans have been produced for the Highways and Public Realm project.

Drop-ins took place on Monday 9 June (4:30pm-7pm) and Wednesday 18 June (4:30pm-7pm) at Ashbourne’s Elim Church, Waterside Business Park, DE6 1DG for members of the public and local businesses to ask questions about the delivery of the highways scheme and raise any issues about the delivery of the wider programme.

Derbyshire County Council is responsible for delivering the current Ashbourne Reborn highways work in the town centre. They are prioritising the re-opening of St John Street which is planned by the end of September, and this remains on schedule, however the overall programme is now expected to complete in early November rather than late October.

This information was accurate on 1 August 2025, although it may change over time.

Ashbourne Reborn Phasing Plan 1 of 2

Phasing plan updated 1 August 25

Dig Street North (closed to traffic)

April to early November ’25

Access maintained for pedestrians and delivery vehicles

Phasing of work within this section:

  1. West side footway due to be open for use before the completion date.
  2. Works at the junction due to complete ahead of St. John St. reopening.
  3. East side footway will follow in phases to maintain access.
  4. Carriageway surfacing will be the last independent activity.

Dig Street South (closed to traffic)

Late January to June ‘25

Access maintained for pedestrians and delivery vehicles

Shrovetide Walk

August to October 2025

Ashbourne Reborn Phasing Plan 2 of 2

Ashbourne Reborn Phasing Plan 2 of 2 1 July 25

Market Place

March to early November ’25

Parking ceased from February

Works Sequence:

  1. Complete tree pits, drainage works and new block paving to the current tarmac area.
  2. Reinstatement to be tied in with HVM installation.
  3. Repair and regrout block paving to follow
  4. Works to the NW (Butchery) Footway will follow completion of the main works.

Buxton Hill

Paving works

February to July ’25

Completion of paving and tie in details.

Carriageway works

June to November’25

  1. Carriageway drainage works.
  2. Last work item will be carriageway resurfacing

St John Street (closed to traffic)

March to September ’25

Access maintained for pedestrians and delivery vehicles

Works Sequence:

  1. North footway to be completed to Millennium Sq. Open for use.
  2. Relocate to South Footway to splitter island.
  3. Complete Paving from Millenium Square to Market Place.
  4. Last work action will be to carry out carriageway surfacing.

Millennium Square

May to August ’25

Victoria Square

July to October ’25

Download a pdf copy of the Phasing Plans

Ashbourne Reborn Phasing Plans as of 1 August 2025